County-Wide Granular Surfacing:

County-wide granular surfacing has begun. There are 30 working days for this project. Expect heavy truck traffic during this project.

County Highway G76 Bridge Replacement:

Bridge replacement over Otter Creek on G76 Hwy is under construction with 100 working days. Please use designated detour route.

Bridge Replacement Project on 190th Ave.:

Bridge Replacement over North Wolf Creek on 190th Ave. is under construction with 90 working days. No detour route has been established for this project.

G76 Hwy Phase III HMA Resurfacing Project:

HMA resurfacing project on G76 Hwy from 200th Ave. east to county line road (250th Ave.). Project has 70 working days. Contract has been signed with Norris Asphalt Paving Company. Construction is underway. A detour route will be established during certain operations of construction otherwise flaggers with a pilot car will be used. Please be aware that there will be delays during the construction of this project, so please pay attention to posted signing and drive with caution.

Nevada Street Phase II Grade and Drain Project:

Farm-to-Market grade and drain project on Nevada Street from R63 Hwy. to 118th Ave. is scheduled to be let in May of 2017.


*All time-frames are tentative and subject to change. This list does not cover all construction operations performed within the county.